Work on the hydro scheme at Rumbling Bridge continues to go according to schedule. The main excavation of the railway siding has been complete and is ready for the pipes to be installed. There is a programme of rock blasting during April that will open up the trench towards the intake weir.
The foundations for the powerhouse are currently being laid. The pipe will be installed from here back toward the intake, so work on the slope up through the village will be starting soon.
Components for the turbine are currently being brought to the factory in Slovenia and we expect it to be delivered on time in early July by which time the powerhouse will be complete and ready to receive it.